Abstract

The Guiniguada Viaduct, located in Las Palmas de Gran Canaria, is an existing structure built in 2003, whose concrete deck was constructed using the cantilever construction method. In 2022, an anomaly was detected consisting of the failure of a significant number of external prestressing tendons. Subsequent inspections revealed a more extensive problem, with deterioration and rupture of numerous continuity tendons located in the bottom slab of the main span. Given the impossibility of fully restoring the structural capacity through internal strengthening, a singular solution was developed consisting of a complementary external prestressing system arranged along the entire box-girder deck. This system is characterized by tendons that pass through the bottom slab and run along the lower end of a central steel deviator strut located at midspan. Its execution required specific construction procedures and singular technical innovations, considering the geometric constraints and the height of the viaduct. The system restored the lost structural capacity and ensured the long-term durability of the structure, representing an unprecedented intervention in the field of strengthening prestressed concrete bridges.

Downloads

Published

2026-04-02

Issue

Section

Papers from Granada Presentations

How to Cite

Llombart Jaques, J. A. (2026). Unique Structural Reinforcement Solution by Underside Deck Stay-Cable System in the Guiniguada Viaduct (Gran Canaria). Hormigón Y Acero. https://doi.org/10.33586/hya.2026.4158